Crushing chest pains. Shortness of breath. Dizziness. Nausea.
We all know the classic warning signs of a heart attack. Most
of us also know that obesity, high cholesterol and inactivity
signal an increased risk of heart disease. It's better
to follow the doctor's advice about lifestyle changes before
a frantic call to 911 is necessary.
Manufacturing companies often find themselves in situations
that parallel those of the heart-conscious individual. Some companies
are hit by crises that clearly threaten their survival. A big
customer takes work overseas or demands a huge price cut, for
example. Other companies take steps to avoid a crisis, adopting
measures to keep them viable and competitive.
Richards Industries in Cincinnati, Ohio, is wisely following
this second course. The company manufactures specialty valves
for a variety of industries, including biotech, pharmaceutical,
chemical, petroleum and power generation. Several years ago,
the company recognized the symptoms of its own "less-than-optimal
lifestyle." Among them were long leadtimes, excessive work
in process, missed delivery dates, lost sales and outages in
finished product inventory.
In response, the company adopted lean manufacturing, a multipronged
approach to systematically reducing waste in all aspects of its
shopfloor operations. Just as individuals have turned their health
around by going on a diet, quitting smoking or starting an exercise
program, Richards Industries has taken some clear steps to protect
and improve its health as a manufacturer.
The company rearranged its machine tools into cells. It moved
part inspection to the shop floor and eliminated a major bottleneck
in the inspection lab. Other bottlenecks, such as long dry times
in the paint department, were also eliminated. Work areas were
reorganized to make them more orderly and less cluttered.
These changes have helped the company shorten leadtimes, slash
batch sizes and reduce work in process. These changes have also
focused the company's attention on another important aspect
of lean manufacturing—setup reduction. Reducing setup time
is essential to reducing leadtimes, batch sizes and work-in-process
levels. So for the last 2 years, the company has worked hard
to adopt quick change-over procedures in its machining operations.
The results have been impressive.
In January 2002, average setup time was 50 minutes. Today,
the average is 27 minutes, almost 50 percent faster. The goal
is 20 minutes, an average the shop expects to hit by the end
of this year.
Today, the typical shop order calls for 20 to 30 pieces to
be processed in a batch. Two years ago, 200 pieces was the norm.
Instead of multiple pallets moving from machine to machine, now
there is usually only one. Small batches can now flow much more
quickly, cutting leadtimes from weeks to days. With shorter leadtimes,
fewer finished items need to be stocked to fill customer orders.
The capital tied up in work in process and in finished goods
inventory can be invested elsewhere.
According to Doug Parham, vice president of operations and the
current "champion" of Richards Industries' lean
initiatives, the shop has almost finished its first round of
setup reduction projects. What sets this effort apart is that
the company has exercised extraordinary discipline and persistence
in this pursuit, striving to maintain a sense of urgency despite
the lack of a glaring emergency. In that regard, the effort has
been outstanding.
In a nutshell, the shop is doing exactly what the doctor ordered.
Wisdom In Maturity
Richards Industries, a privately held company, has been manufacturing
specialty valves since 1947. It has four lines of distinctly
different valves and related products. The three main valve lines
are Jordan Valve (valves and regulators), Marwin Valve (ball
valves) and Hex Valve (instrument manifolds, orifice block valves,
gauge valves, needle valves and block and bleed valves). The
Bestobell line of steam traps completes the range. All of these
products can be ordered as standard items, but the company has
made a specialty of custom engineering variations for critical
or unusual applications.
For the most part, the machining processes used to produce
these valves are unremarkable. The machine shop is populated
mainly with older CNC lathes and mills, about 30 machines in
all. However, the shop has kept up with advances in cutting tools,
coolants and programming techniques.
Gilbert Richards, the company owner, has consistently taken
a keen interest in the company's performance and in the
well-being of its employees. About 3 years ago, he began studying
lean manufacturing as a promising concept for improving the company's
overall performance and profitability.
He and his top managers recognized some key facts about the
company's business. In a mature industry, the company would
have to compete on price and responsiveness to customers. Sales
were not likely to expand in response to new product technology.
Likewise, cycle times on the shop floor were not likely to yield
significant improvements. To prosper, if not to grow, the company
needed to get lean.
The Road To Lean
In 2001, Richards Industries invited productivity consultants
from TechSolve, also a Cincinnati-based firm, to audit the shop's
operations and recommend a path to lean manufacturing. Initial
studies of work flow revealed a situation common in many companies.
Bottlenecks in the machining area were causing skids of workpieces
to accumulate in queues, especially at certain machines. Because
machine tools were grouped by type, workpieces often traveled
long distances, moving back and forth between departments. All
inspection was done in a centralized quality control lab, so
parts routinely encountered long delays before moving to the
next process.
Among the recommendations was a plan to group the machine
tools into "product manufacturing areas." Because
the four main valve product lines are so distinct in design and
function, they have no parts in common, sharing only certain
raw materials such as barstock. Therefore, it made sense to move
all of the machines devoted to machining components for each
line into separate cells. Each cell would function as a mini
job shop capable of producing all of the machined parts required
to complete a certain valve product. Raw material entering each
cell would stay within that cell until it is ready to move to
the assembly area, paint station or finished parts storage.
As this plan was being studied, a series of general training
sessions on lean manufacturing was also launched for company
employees.
In January 2002, Mr. Parham came on board to lead the company's
implementation of lean manufacturing. Mr. Parham had been employed
at another local company, where he had spearheaded several lean
manufacturing initiatives.
"It was clear that excessive work in process and finished
inventory were major problems," Mr. Parham recalls. "When
I arrived, I found a company with solid product lines, a stable
and dedicated workforce, a management team committed to improvement—and
a factory crowded with work in process." Just as the problems
were clear, Mr. Parham believed that the solution was equally
clear: The company had to reduce its setup time.
The Change-Over Challenge
Mr. Parham challenged the shop to reduce setup time from 50
minutes to 20. At first, the challenge was greeted with some
scoffing and skepticism, but also with a willingness to try.
Mr. Parham's past training and prior experience with setup
reduction gave him confidence that this goal was not unrealistic. "I
knew that other shops have been able to reduce setup time by
50 to 75 percent, usually without bringing in new technology.
I was sure we could do it here as well," he says.
The first step was to go ahead with the plans for regrouping
the machine tools into cells. In this arrangement, machines could
share common setup areas, tool storage and fixturing items. This
set the stage for setup reduction.
Mr. Parham also made sure that everyone understood how setup
was defined in the context of lean manufacturing. Setup is the
time between the last good piece of the current run and the first
good piece of the next run.
It's not about cycle time—how fast the machine
completes a part. Setup covers more than loading and unloading
workpieces. Setup covers more than fixturing and clamping strategies.
The next step was to identify the worst bottlenecks—the
machines with the longest setup times. These bottlenecks offered
the opportunity for the biggest initial improvements. Dealing
with these "monuments" became the shop's first
priority.
After that, the plan was to follow a series of "setup
reduction events" as practiced by most lean manufacturing
experts. Each event follows four steps:
- Document the current change-over.
- Determine what
setup steps can be done while the machine is still running.
- Streamline
setup steps that must be done while the machine is not running.
- Put
the basics in place for workplace organization and visual control.
The company set out to apply this process systematically,
one machine at a time, starting with those machines that had
the longest setups. Each "setup reduction event" took
about a week. The first was held in February 2002.
"One of the first things we learned is that we needed
to apply 5S throughout the shop right away," says Mr. Parham,
referring to the workplace organization system based on the principles
of sort, shine, simplify, standardize and sustain. 5S is designed
to create an efficient workplace in which clutter, disorder and
extra steps are brought under control.
After 3 months of applying 5S, each cell was noticeably less
cluttered and more orderly. Activities were easier to observe.
Work flow was easier to monitor. 5S made subsequent setup reduction
events more effective.
How Events Take Place
Each setup reduction event begins by videotaping one or two
complete setups, recording every action the operator performs
in a part change-over. A time-marker on the video camera allows
reviewers to construct a detailed sequence of setup activities,
which is recorded in a computerized spreadsheet. How long each
step takes is derived from the time-marker readings.
Although creating this "element breakdown" spreadsheet
can be tedious, Mr. Parham insists that it is worth the effort. "It
allows an objective analysis of existing setup procedures," he
says. It also takes some of the emotion out of the setup reduction
event. "It has to be clear that this is not about finding
fault, but about turning good processes into better ones."
After the videotaping and element breakdown are complete,
a team is put together to conduct a brainstorming session. Its
purpose is to come up with all of the ways setup can be reduced
and to sort out the best of these ideas. The team includes the
operator from each shift, a manufacturing engineer and a CNC
programmer. Representatives from other departments are designated
to be on standby if their input is needed. These representatives
include someone from design engineering, purchasing, production
planning and inventory control. If called, these individuals
are ready to join the meeting to offer suggestions or comments
from their perspectives.
Structuring the team is important, Mr. Parham says. "You
want to exclude anyone who hampers the free flow of ideas. Someone
with an authoritarian or judgmental attitude spoils the atmosphere
and makes it difficult for others to freely speak their minds
and share ideas," he says. "It has to be understood
that every idea will be evaluated fairly and considered solely
on its own merits. No idea is too crazy to consider."
Brainstorming sessions follow a standard agenda shared with
the group before the session starts. The five steps are:
- Review the video and element breakdown.
- Brainstorm and discuss ideas to improve.
- List action items
Assign responsibilities.
- Schedule and implement the plan.
When reviewing the element breakdown, the team immediately
determines which setup elements are external and which are internal.
External steps, those that can be done while the machine is running,
can be pulled out of setup right away, but procedures must be
developed to ensure that these steps are completed before a current
run is finished. External steps include getting parts, fixtures,
gauges and cutting tools ready for the next run.
Internal steps, those that must take place when the machine
is not running, must be streamlined. This is usually a matter
of organizing the workspace. Having all tools ready and within
reach is an example.
The list on this page helps team members think about ways to
reduce setup. Ideas from the brainstorming session are collected
and organized.
"The challenge is to do this first round of setup events
without spending any money," Mr. Parham says. (This does
not count any investments for 5S applications, such as constructing
shadow boards, new shelving, storage units and so on.) Trying
to hold a zero budget encourages the team to concentrate on the
root causes of waste rather than treating its symptoms. Extra
steps, waiting time, miscommunication and other causes of waste
can usually be resolved without incurring costs.
Although setup reduction events focus on one machine or one
change-over requirement, many of the suggestions could be implemented
elsewhere at the same time. For example, one of the early events
uncovered the fact that operators were not saving the programs
that they created and debugged at the machine tool. This habit
stemmed partly from operator preferences for certain programming
techniques. Operators were routinely recreating programs and
debugging them each time. Now, all of these programs are archived
in memory at the machine controller, and they are also saved
in appropriate directories on the file server of the shop's
computer network.
Another typical outcome of an event was determining what consumable
tooling items could be stored at each machine tool or workstation.
As this and other point-of-use storage opportunities were discovered,
the shop eventually closed its centralized toolroom and cleared
the space for other uses.
On the last day of an event, the team reaches a consensus
on what actions to take, who is responsible for each action and
when the actions are to be completed. The group also decides
when to reconvene to review progress and make modifications to
the plan.
The Next Round
In February 2004, two more setup reduction events took place. "We
were actually revisiting machines where change-over times were
still higher than we expected them to be," Mr. Parham explains.
He is quick to add that setup reduction is not something you
do and then move on. The shop plans to repeat the series of setup
reduction events as it strives to reduce change-over time even
further. There is always room for improvement.
The second round of events will follow the same procedures
that were used in the first. Both internal and external elements
will be scrutinized, although internal elements, the ones that
must take place while the machine is not running, are likely
to get more attention. "That's when the clock is
ticking, and every second saved ultimately reduces leadtimes," Mr.
Parham says.
This is also the point to consider capital investments to
streamline change-over procedures, he adds. A shop might consider
adding pallet changers to VMCs, for example. Automation, such
as automated gantry loaders for lathes, may be the answer in
other cases. The return on such investments, however, will be
clear because the effect on leadtimes can be easily demonstrated
and documented.
Mr. Parham also says that the second round of setup events
is a prelude to reviewing machine capability. In other words,
the shop will study cycle times to see where productivity gains
might be found. At this point, saving a few seconds here and
there makes a difference, unlike situations in which shorter
cycle times only add to longer queues at the next machine.
Ideally, the shop wants to reach the point at which quick
change-over allows single-piece part flow. "Eventually,
we want to link the release of each shop order to an incoming
customer order and produce it at the same cost and leadtime,
even if the order produces a lot size of one," Mr. Parham
says.
No End In Sight
Just as the right diet and proper exercise are part of a healthy
lifestyle and not a short-term treatment plan, lean manufacturing
is a "lifestyle," too. Sustaining the effort is at
the essence of the concept.
Lean manufacturing implies that a shop never stops working
on setup time reduction. Mr. Parham believes that this is the
most important lesson that Richards Industries has learned. There's
no end in sight. But there's no end in sight to the company's
ability to compete in its chosen niche, either. And that's
what lean manufacturing is all about.