VERISURF
Published

Planning Your Resources Wisely

Unless you are one of a small number of companies that possesses all the resources you need to complete any job you get, you are faced with a tough manufacturing decision: how to properly allocate your resources.

Share

 

If you are “waste conscious,” you already understand that time spent producing parts that will not be shipped out for some time is overproduction, and this wastes resources. Other wastes, such as over-processing parts, also drain resources.
 
So assuming we are not overproducing, over-processing or doing other things that prevent us from using our resources to their fullest, how do we best use our limited resources? Here is where an understanding of TAKT time, and how it can be applied to your operation, can help.
 
Simply put, TAKT is the rate of customer demand and the target to which we must gear our manufacturing processes. TAKT is determined by a simple calculation—work time available divided by the demand for product during that time. For example, say a machine works two 8-hour shifts with two 10-minute breaks per shift, and the machine needs to produce 800 parts per day to meet customer demand. TAKT, in this example, is calculated as follows: (2 × 480 minutes of machining time)-(4 × 10 minutes of break time) ÷ 800 parts = 1.15 minutes, or 69 seconds. This means that each step in the manufacturing process must be capable of completing a part within that 69-second target. When planning which resources to use to produce a part, the cycle time (time to produce one part) for each resource needs to be compared to TAKT time. 
 
Let’s assume we are trying to select the best machine to produce the part described in the previous scenario. One machine can complete the part in 50 seconds, and another can complete the part in 58 seconds. We can see right away that both machines can meet the daily requirement for this part because each cycle time is less than the TAKT time of 69 seconds.
 
However, to make the best resource decision, it would be helpful to see how much of each machine’s daily available time would need to be dedicated to this one part. For the machine with the 50-second cycle time, 72 percent of available time (50 seconds of cycle time ÷ 69 seconds of TAKT time), or a little more than 11 hours each day, must be dedicated to this one part. For the machine with the 58 second cycle time, 84 percent of available time (58 seconds of cycle time ÷ 69 seconds of TAKT time), or almost 13 hours each day, must be dedicated to this one part. 
 
Based on the above result, many would draw the conclusion that it is best to assign the job to the faster machine. This may be sound reasoning, but only if you can put the remaining time (a little more than four hours per day) to effective use, perhaps by changing over and running another job during this time. If not, you are faced with two choices: The first is to overproduce and make more than 800 parts per day on the faster machine, incurring the risk that accompanies a decision to produce beyond the daily committed demand. The second is to let the machine sit idle during this period. 
 
In this case, the alternative choice of running the 800 parts on the slower machine is worth considering for a number of reasons. First, the machine can meet the needs of TAKT. In other words, it can produce all the parts required each day. Second, it actually frees up the faster machine to produce other parts. If change-over times are short, it could possibly produce a number of different parts during the two-shift operation. Third, creative machine programming and fixturing could allow this machine to run many parts during a machine cycle, thereby allowing the machine operator to do other things while the machine continues to cut chips. Finally, with a part cycle time that is less than but still relatively close to the TAKT time (actually, 84 percent of TAKT time), this could be an ideal situation to accommodate any problems or delays that might occur. Not that we want to accept waste in our process, but it is not advisable for cycle time to be too close to the TAKT requirement, as this limits flexibility and provides no cushion if the unexpected occurs.
 
Comparing machine cycle times (what can be done) to TAKT times (what needs to be done) is an effective way to help plan your resources. However, be prepared for some unexpected outcomes, such as “faster is not always
better.”
VERISURF
Paperless Parts
Precision grinding & hard turning custom solutions
IMTS 2024
MMS Top Shops
Gardner Business Intelligence
Kennametal
Koma Precision
IMTS 2024
Norton Superabrasives Wheels  Paradigm Plus
Mazak Multi-Tasking: Your Parts Multiplier.
VERISURF

Related Content

Milling Tools

10 Tips for Titanium

Simple process considerations can increase your productivity in milling titanium alloys.

Read More
Basics

How To Calibrate Your Calipers

If you’re interested in calibrating your own digital, dial or Vernier calipers, here are some steps to take to make sure it goes off without a hitch.

Read More
Basics

7 CNC Parameters You Should Know

Parameters tell the CNC every little detail about the specific machine tool being used, and how all CNC features and functions are to be utilized.

Read More
Basics

Threading On A Lathe

The right choices in tooling and technique can optimize the thread turning process.

Read More

Read Next

Vertical Machining Centers

The Cut Scene: The Finer Details of Large-Format Machining

Small details and features can have an outsized impact on large parts, such as Barbco’s collapsible utility drill head.

Read More

3 Mistakes That Cause CNC Programs to Fail

Despite enhancements to manufacturing technology, there are still issues today that can cause programs to fail. These failures can cause lost time, scrapped parts, damaged machines and even injured operators.

Read More
VERISURF